Parent Page: Project Manager Brain
Version: 1.0
Date: 2026-06-23
Author: HeadOffice
Status: Active
Page Type: Brain Operating Model
Authority Level: MWMS Operating Model
Purpose
Project Manager Brain Operating Model defines how Project Manager Brain operates day to day across MWMS.
It translates Project Manager Brain Canon and Project Manager Brain Architecture into practical execution behaviour.
This Operating Model defines:
- how projects enter the system
- how projects are approved
- how work is divided
- how priorities are set
- how daily work is selected
- how dependencies are managed
- how blockers are handled
- how changes are recorded
- how meeting actions become approved work
- how testing and acceptance are controlled
- how version alignment is monitored
- how HeadOffice, Operations, Kaizen, SIT and specialist Brains coordinate
- how project state is reviewed
- how completion is confirmed
- how future work is prepared
- how work is escalated
Operating Position
Project Manager Brain is the operational coordination layer between approved MWMS direction and completed execution.
Its operating role is:
To maintain a current, reliable and explainable execution picture across all active MWMS projects and to coordinate the next valid work without replacing strategic or specialist authority.
Project Manager Brain must continuously reconcile:
- approved direction
- current project state
- current task state
- available people
- dependencies
- blockers
- testing requirements
- version state
- change history
- meeting outcomes
- future work
- completion evidence
Operating Principles
Project Manager Brain must operate according to the following principles.
Current Reality Before Planned Reality
The system must reflect the true operational state before adding more future work.
Priority Before Activity
Work must be selected because it is the right work, not merely because it is available or recently discussed.
Readiness Before Start
Tasks must not begin before required inputs, authority and dependencies are confirmed.
Evidence Before Completion
Work must not be accepted without the evidence required by its acceptance criteria.
Testing Before Closure
Implementation alone does not justify closure.
Change Before Continuation
When direction changes, affected records must be updated before work continues under outdated assumptions.
One Trusted Save Point
Every active project must maintain one current trusted save point.
Visible Blockers
Blocked work must remain visibly blocked.
Explainable Priority
Project Manager Brain must be able to explain why one task is ahead of another.
Human Authority
AI recommendations must remain subordinate to approved human decisions.
Specialist Ownership
Specialist Brains retain ownership of specialist work.
Controlled Future Work
Future ideas must remain organised without overwhelming the current execution focus.
Primary Operating Cycle
The primary Project Manager Brain operating cycle is:
Direction
To
Project Definition
To
Project Approval
To
Workstream Structure
To
Task Structure
To
Priority And Readiness Review
To
Execution
To
Update
To
Testing
To
Acceptance
To
Save Point
To
Next Valid Action
To
Reporting
The cycle repeats until the project is completed, closed or cancelled.
Project Intake Operating Model
Project Sources
A proposed project may originate from:
- HeadOffice direction
- a specialist Brain requirement
- an identified system failure
- a Kaizen improvement
- a SIT finding
- an approved meeting decision
- a version alignment requirement
- a technical dependency
- an AIBS product requirement
- an approved client requirement in future
- a regulatory or compliance requirement
- a testing failure
- an approved strategic opportunity
Project Intake Requirements
A proposed project must include:
- project title
- project objective
- reason for the project
- source
- proposed owner
- affected Brain or system
- expected outcome
- initial priority
- known dependencies
- known risks
- approval requirement
A project must not become active merely because it was suggested.
Project Intake States
The approved intake states are:
- Draft
- Proposed
- Under Review
- Approved
- Rejected
- Deferred
- Cancelled
Project Approval
Project approval should confirm:
- the project is authorised
- the objective is clear
- the owner is confirmed
- the expected outcome is clear
- the priority is justified
- the scope is understood
- known dependencies are recorded
- acceptance criteria can be defined
- the project does not duplicate existing work
- the project fits current MWMS priorities
HeadOffice approval is required for projects that materially affect:
- strategic direction
- multiple Brains
- major resource allocation
- financial commitments
- system architecture
- AIBS product direction
- major project sequencing
- significant risk
Project Setup Operating Model
Once approved, the project must be structured before active execution begins.
Project setup must include:
- project record
- owner
- contributors
- project status
- current phase
- project priority
- acceptance criteria
- initial save point
- known risks
- known blockers
- known dependencies
- related MCR pages
- related operational pages
- initial workstreams
- initial tasks
- next valid action
The project must not be activated if the first valid action is unknown.
Workstream Operating Model
Workstreams should be used when a project contains multiple meaningful execution areas.
Workstreams may represent:
- build phases
- system areas
- functional areas
- delivery groups
- testing groups
- integration areas
- migration phases
- client delivery phases in future
Workstreams must not be created merely to add administrative layers.
Each workstream must have:
- clear objective
- parent project
- owner where applicable
- status
- priority
- sequence
- linked tasks
- acceptance criteria
- current blocker state
- current dependency state
- next valid action
Task Operating Model
Task Creation
Tasks may be created from:
- approved project planning
- approved meeting actions
- change impact review
- test failure
- SIT finding
- Kaizen finding
- dependency resolution
- HeadOffice direction
- specialist Brain requirement
- project review
- save-point review
Task Quality Check
Before a task becomes Ready, confirm:
- the action is specific
- the affected object is identified
- the owner is confirmed
- the project is linked
- the workstream is linked where applicable
- the required outcome is clear
- dependencies are known
- the acceptance criteria are clear
- testing requirements are known
- evidence requirements are known
- the task is authorised
Task Readiness States
Task readiness should be classified as:
- Not Defined
- Missing Owner
- Missing Input
- Waiting For Decision
- Waiting For Dependency
- Ready
- Blocked
- Not Authorised
Only Ready tasks should normally enter active prioritisation.
Task Ownership
Every active task must have one accountable owner.
Contributors may be listed, but accountability must not be diluted across multiple unnamed owners.
The owner is responsible for:
- updating task status
- reporting blockers
- providing implementation evidence
- submitting the task for testing
- responding to failed tests
- confirming when the task is ready for acceptance
Task Progression
The normal task progression is:
Not Started
To
Ready
To
In Progress
To
Implemented
To
Ready For Testing
To
Testing In Progress
To
Test Passed
To
Awaiting Acceptance
To
Accepted
To
Closed
Alternative paths include:
Testing In Progress
To
Test Failed
To
Changes Required
To
Retest Required
To
Testing In Progress
Tasks may also move to:
- Blocked
- Paused
- Cancelled
- Archived
Status changes must reflect reality.
Priority Operating Model
Priority Inputs
Project Manager Brain must consider:
- HeadOffice strategic priority
- project priority
- current main goal
- dependency impact
- work unlocked
- system risk
- commercial impact
- testing urgency
- consequences of delay
- owner availability
- readiness
- effort
- context switching
- external deadline
- version alignment risk
- SIT severity
- Kaizen recurrence
- current project phase
- specialist Brain readiness
Priority Recommendation
Project Manager Brain may generate a recommended order.
The recommendation must include:
- recommended priority
- reason
- key dependency
- key risk
- expected result
- consequence of delay
- work unlocked
- owner readiness
Human Priority Approval
Martyn, HeadOffice or another authorised role may approve or override the recommendation.
Any material override should record:
- previous recommendation
- approved priority
- override reason
- approving authority
- date
Priority Categories
Approved operational categories are:
- Must Do Today
- Should Do Today
- Ready If Capacity Allows
- Testing Required
- HeadOffice Decision Required
- Waiting
- Blocked
- Ready Next
- Scheduled Future Work
- High Value But Not Ready
- Retest Required
- Version Alignment Required
- Deferred
- Parking
- Do Not Touch
Daily Work Operating Model
Daily Review Purpose
The daily review determines what valid work should happen today.
It must not become a broad planning meeting that repeatedly reopens settled strategy.
Daily Inputs
The daily review should consider:
- current save points
- unfinished work from the prior day
- Must Do Today tasks
- active blockers
- tests awaiting action
- failed tests
- HeadOffice decisions required
- version warnings
- newly approved changes
- owner availability
- available working time
- near-future work that may become ready
Daily Output
The daily output should show:
- current main project
- current main workstream
- Martyn’s priority tasks
- M’s priority tasks
- tests requiring action
- blockers requiring removal
- decisions requiring approval
- work that should not be touched
- next valid task
- tasks likely to become ready next
- material changes since the last review
- version or dependency warnings
Daily Task Limits
The system should avoid unrealistic daily plans.
Daily selection should account for:
- task size
- available time
- interruption risk
- context switching
- dependency uncertainty
- testing time
- review time
- corrective work
- existing unfinished tasks
A smaller realistic task list is preferred over a large aspirational list.
Weekly Review Operating Model
Weekly Review Purpose
The weekly review confirms overall project movement and future readiness.
Weekly Inputs
The weekly review should consider:
- projects advanced
- projects stalled
- workstreams completed
- tasks completed
- tasks reopened
- blockers added
- blockers resolved
- tests passed
- tests failed
- changes approved
- decisions made
- version changes
- SIT findings
- Kaizen findings
- next week readiness
- capacity concerns
Weekly Output
The weekly report should include:
- key outcomes
- meaningful movement
- projects at risk
- unresolved blockers
- failed tests
- decisions required
- version concerns
- next week priorities
- work that should remain deferred
- major lessons
- required escalations
Project Review Operating Model
Every active project should be reviewed at a frequency appropriate to its importance and pace.
The project review must confirm:
- objective remains valid
- owner remains correct
- project status remains accurate
- priority remains justified
- workstreams remain relevant
- tasks remain current
- dependencies remain accurate
- blockers remain visible
- decisions are recorded
- changes are reflected
- testing state is correct
- version state is current
- save point is current
- next valid action is known
A project must not remain Active when there is no active or ready work.
Dependency Operating Model
Dependency Identification
Dependencies should be identified during:
- project setup
- workstream setup
- task setup
- change review
- meeting review
- testing
- version review
- SIT review
- Kaizen review
- project review
Dependency Classification
Dependencies may be classified as:
- task dependency
- project dependency
- Brain dependency
- owner dependency
- decision dependency
- test dependency
- page dependency
- plugin dependency
- schema dependency
- Canon dependency
- external dependency
- access dependency
- evidence dependency
Dependency Review
Each dependency should confirm:
- dependent item
- required item
- owner
- status
- expected resolution
- delay impact
- work unlocked
- escalation need
A dependency should be marked Satisfied only when the required condition is genuinely met.
Blocker Operating Model
Blocker Identification
A blocker exists when work cannot validly proceed.
Common blocker sources include:
- missing decision
- unavailable owner
- failed test
- missing access
- missing data
- missing specification
- unresolved dependency
- version mismatch
- broken plugin
- broken schema
- unclear acceptance criteria
- conflicting direction
- missing evidence
- unresolved SIT finding
Blocker Response
The blocker process is:
Blocker Identified
To
Impact Assessed
To
Owner Assigned
To
Resolution Action Defined
To
Escalation Need Checked
To
Resolution Attempted
To
Evidence Recorded
To
Blocker Resolved Or Accepted
Blocked tasks must not be shown as ready.
Change And Decision Operating Model
Decision Capture
Material decisions must be recorded when they affect:
- project scope
- project priority
- ownership
- build order
- acceptance criteria
- system architecture
- Brain authority
- plugin behaviour
- schema structure
- testing
- version alignment
- project continuation
- project cancellation
Change Review
Every approved change must trigger an impact review.
The review should ask:
- which projects are affected
- which workstreams are affected
- which tasks are invalid
- which tasks must be added
- which priorities change
- which dependencies change
- which pages change
- which plugins change
- which schemas change
- which versions change
- which tests become invalid
- which retests are required
- whether a new save point is required
- whether HeadOffice must review
Work should not continue under an outdated plan after a material approved change.
Meeting Operating Model
Meeting Intake
A meeting record should capture:
- title
- date
- attendees
- notes
- recording where applicable
- related projects
- related Brains
- source owner
Action Extraction
Project Manager Brain may extract proposed:
- decisions
- actions
- owners
- due dates
- blockers
- risks
- changes
- cancellations
- follow-up items
- unresolved questions
Human Review
Extracted items must be reviewed before approval.
The reviewer should classify each item as:
- Approved Decision
- Approved Action
- Approved Change
- Approved Risk
- Approved Blocker
- Question
- Suggestion
- Rejected
- Duplicate
- Already Recorded
- No Action Required
Approved Application
Approved meeting items may then:
- create a task
- update a task
- change an owner
- create a decision
- create a change
- create a blocker
- create a dependency
- update project status
- trigger testing
- trigger version review
- trigger escalation
Testing Operating Model
Test Planning
Testing should be defined before final acceptance.
A test must state:
- what is being tested
- why it is being tested
- expected result
- test method
- test owner
- required evidence
- acceptance effect
Test Execution
The test owner records:
- actual result
- evidence
- pass or fail
- failure details
- corrective action required
- retest requirement
Failed Tests
A failed test must:
- remain visible
- prevent acceptance where relevant
- create or link corrective work
- define retest requirements
- update project or task state
- update the save point
A failed test must not be removed merely because the implementation was changed later.
The retest should provide the new result.
Acceptance Operating Model
Acceptance Review
Acceptance should confirm:
- defined criteria were met
- required tests passed
- required evidence exists
- dependencies are satisfied
- required documentation is updated
- required versions are recorded
- required MCR updates are complete
- no unresolved critical SIT finding remains
- no unresolved critical blocker remains
Acceptance Outcomes
The approved outcomes are:
- Accepted
- Accepted With Conditions
- Rejected
- Changes Required
- Retest Required
- Escalation Required
Project closure should require all critical acceptance conditions to be resolved.
Save-Point Operating Model
Save-Point Timing
A save point should be created or updated when:
- a meaningful build stage is completed
- a plugin version changes
- a schema changes
- a major test completes
- a major change is approved
- a workstream completes
- a project pauses
- a project is handed over
- a project is closed
- a new session needs a trusted continuation point
Save-Point Content
The save point should include:
- project name
- date
- active version
- completed work
- current active work
- testing state
- blockers
- dependencies
- deferred work
- risks
- recent decisions
- recent changes
- next valid action
- work that must not be touched
- required evidence links
The save point must be concise enough to use but complete enough to restore the project state.
Version Alignment Operating Model
Version Review Events
Version alignment should be reviewed when:
- a plugin version changes
- a schema version changes
- Canon changes
- an operational workflow changes
- a handoff changes
- a dependent Brain changes
- testing exposes incompatibility
- SIT identifies drift
- a project reaches acceptance
- a project is handed over
Version Review Questions
The review should ask:
- what changed
- which version is now active
- which systems depend on it
- whether dependencies remain compatible
- whether documentation is current
- whether tests remain valid
- whether retesting is required
- whether another Brain must update
- whether the save point remains valid
Version Alignment States
Approved states are:
- Aligned
- Review Required
- Update Required
- Retest Required
- At Risk
- Misaligned
- Blocked By Mismatch
- Unknown
Kaizen Operating Model
Kaizen Intake
Kaizen may submit:
- repeated friction
- repeated delay
- duplicated effort
- recurring test failure
- workflow inefficiency
- handoff failure
- avoidable manual work
- process improvement opportunity
Kaizen Review
Project Manager Brain should assess:
- frequency
- impact
- effort
- urgency
- risk reduction
- work unlocked
- current priority conflict
- readiness
- ownership
Approved Kaizen work may become:
- task
- workstream
- improvement project
- process change
- test requirement
- future work item
SIT Operating Model
SIT Intake
SIT may submit findings concerning:
- false completion
- missing evidence
- unreliable implementation
- broken workflow
- drift
- inconsistent versions
- weak testing
- unresolved risk
- rescue need
SIT Finding Handling
A valid SIT finding must:
- be recorded
- be linked to affected work
- receive severity
- receive owner
- receive corrective action
- receive retest requirement where applicable
- affect acceptance where relevant
- remain visible until resolved or formally accepted
Critical SIT findings must be escalated.
HeadOffice Operating Model
HeadOffice Inputs
HeadOffice may provide:
- strategic direction
- portfolio priority
- project approval
- project cancellation
- major scope changes
- risk acceptance
- resource decisions
- cross-Brain authority decisions
- escalation outcomes
Project Manager Brain Outputs To HeadOffice
Project Manager Brain should provide:
- project health
- priority conflicts
- major blockers
- failed critical tests
- version misalignment
- strategic decisions required
- resource conflicts
- project viability concerns
- consequences of delay
- recommended action
HeadOffice should receive only the level of detail needed for decision and control.
Operations Brain Operating Model
Project Manager Brain should use Operations Brain for:
- execution sequencing
- handoff design
- process continuity
- dependency coordination
- bottleneck analysis
- workflow stability
- operational timing
Operations Brain outputs should influence execution design but should not create unapproved strategic priorities.
Specialist Brain Operating Model
Specialist Brains are responsible for:
- specialist analysis
- specialist execution
- specialist deliverables
- specialist testing requirements
- specialist evidence
- specialist blockers
- specialist handoffs
- specialist version changes
Project Manager Brain is responsible for:
- recording the work
- coordinating timing
- tracking dependencies
- tracking status
- coordinating testing
- coordinating acceptance
- reporting outcomes
- preserving save points
Escalation Operating Model
Escalation Triggers
Escalation should occur when:
- authority is unclear
- priorities conflict
- critical work is blocked
- critical testing fails
- SIT identifies serious failure
- version mismatch threatens operations
- resources are insufficient
- project scope changes materially
- evidence is disputed
- project viability is uncertain
- work proceeds without authority
- specialist Brains disagree materially
- delay consequences are significant
Escalation Format
Each escalation should state:
- issue
- project
- impact
- urgency
- evidence
- options
- recommendation
- decision required
- consequence of no decision
Escalations must not be vague complaints.
Reporting Operating Model
Daily Report
The daily report should focus on:
- current main focus
- today’s valid tasks
- blockers
- tests
- decisions
- next actions
- work unlocked
- warnings
Weekly Report
The weekly report should focus on:
- outcomes
- movement
- failed work
- delayed work
- resolved blockers
- new blockers
- test outcomes
- changes
- versions
- next week
- escalations
Project Status Report
The project report should focus on:
- objective
- current phase
- current save point
- progress
- blockers
- dependencies
- tests
- version
- risks
- decisions
- next action
Reporting must remain action-driven.
Archive Operating Model
Projects, workstreams and tasks may be archived when:
- completed and no longer active
- cancelled
- replaced
- no longer operationally relevant
- retained for historical reference
Archived records must remain readable and linked.
Archived records should not receive ordinary edits.
Reactivation should require explicit action and reason.
Initial Human Roles
Martyn
Primary responsibilities:
- approve projects
- confirm priorities
- approve major changes
- approve decisions
- review daily work
- accept critical work
- resolve escalations
- control settings
- confirm HeadOffice direction
M
Primary responsibilities:
- execute assigned work
- update tasks
- raise blockers
- provide evidence
- submit work for testing
- respond to failed tests
- contribute to project updates
- confirm implementation state
Project Manager Brain
Primary responsibilities:
- organise records
- coordinate execution
- recommend priorities
- identify dependencies
- track blockers
- prepare reports
- identify missing information
- maintain save points
- recommend next actions
- flag risks and misalignment
AI must not be treated as the accountable human owner of critical work.
First Operational Validation
The first operational validation project is:
Content Brain Operational Build
The operating model must prove that it can:
- create the project
- record the objective
- record the current plugin version
- record the current save point
- create workstreams
- create tasks
- assign owners
- record completed work
- record active work
- record archived work
- record testing state
- record blockers
- record dependencies
- record deferred work
- record decisions
- identify next valid action
- generate a daily view
- generate a project report
- confirm version alignment
The Project Manager Brain operating model should not be considered validated until the Content Brain project accurately matches operational reality.
Initial Operating Limits
During the first build:
- all critical changes require human review
- all project approvals require human approval
- all meeting actions require human approval
- all acceptance decisions require human approval
- all priority overrides must be recorded
- all version changes must be confirmed
- all permanent deletions remain prohibited unless explicitly authorised
- all AI recommendations remain advisory
- no autonomous project closure is allowed
- no client-facing operations are enabled
- no unsupported deadlines are generated
Operating Model Success Criteria
The Operating Model is functioning when:
- daily work is clear
- tasks are specific
- owners are clear
- priorities are explainable
- dependencies are visible
- blockers are visible
- meetings create controlled actions
- changes update affected work
- tests remain linked
- acceptance requires evidence
- save points remain current
- version alignment is visible
- HeadOffice receives useful escalations
- future work remains controlled
- specialist authority remains intact
- the next valid action is known
Operating Model Failure Conditions
The Operating Model is failing when:
- task lists become vague
- records fall behind reality
- owners are unclear
- priorities become arbitrary
- blocked work is shown as active
- meetings create unreviewed changes
- failed tests are hidden
- acceptance lacks evidence
- save points are outdated
- version changes are ignored
- future work overwhelms today’s priorities
- HeadOffice must manually reconstruct project state
- Project Manager Brain begins making strategy
- specialist Brains lose authority
- AI actions bypass human approval
MWMS System Change Log
Version: 1.0
Date: 2026-06-23
Author: HeadOffice
Change
Created the initial Project Manager Brain Operating Model.
Defined how projects enter the system, how work is structured, how priorities are approved, how daily and weekly reviews operate, how dependencies and blockers are managed, how meeting actions are reviewed, how testing and acceptance are controlled, how save points are maintained and how version alignment is monitored.
Defined operating relationships with HeadOffice Brain, Operations Brain, Kaizen, SIT Brain and specialist Brains.
Established Content Brain Operational Build as the first live validation project.
Change Impact Declaration
This change establishes the practical operating behaviour required to run Project Manager Brain.
The change does not authorise autonomous strategy, autonomous project approval, autonomous meeting action approval or autonomous completion acceptance.
The change requires human review for critical project, priority, change, testing, acceptance and version decisions.
Pages Created
Project Manager Brain Operating Model
Pages Updated
None
Pages Deprecated
None
Standalone Pages Not Created
Project Manager Brain Workflow Map
Project Manager Brain Page Registry
Project Manager Brain Daily Review Protocol
Project Manager Brain Weekly Review Protocol
Project Manager Brain Project Intake Standard
Project Manager Brain Save Point Standard
The Workflow Map and Page Registry remain scheduled as separate foundation pages.
The remaining pages are not created at this stage and should only be introduced if the operational build demonstrates a clear need.
Registries Requiring Update
MWMS Brain Registry
MWMS Page Parent Map
MWMS Document Registry
MWMS Brain Interaction Map
Project Manager Brain Page Registry once created
Canon Version Update Required
No
Project Manager Brain Canon remains at v1.0.
Change Log Entry Required
Yes
This change must be recorded in MWMS System Change Log 2026 06 16 To 2026 06 30.
Strategic Absorption Result
The Project Manager Brain architecture has been converted into a practical operating model.
MWMS now has a defined method for moving approved projects from intake through prioritisation, execution, testing, acceptance, save-point control, version alignment and reporting while preserving human authority and specialist Brain ownership.
END OF FULL FILE OUTPUT